In support of the NTA controls upgrade project, work will be completed on the 4th and 5th floors on three consecutive Friday evenings as identified below. Airflows to area on the 4th floor will be affected on January 15th and January 29th. As a precautionary measure, no work may take place in the 4th floor ABSL3 suites during these outages. Minimal impact is expected to space temperature and humidity on the 4th and 5th floor animal areas during these outages.

January 15th, 6:00 PM to 11:55 PM: Modifications to 4th floor bathroom and shower exhaust air system. No research work may take place in the 4th floor ABSL3 suites during this outage.
January 22nd, 6:00 PM to 11:55 PM: Modifications to the 5th floor bathroom and shower exhaust air system.
January 29th, 6:00 PM to 11:55 PM: Modifications to 4th floor shower supply air system. No research work may take place in the 4th floor ABSL3 suites during this outage.