During the next four weekends (February 5th through February 28th), Clayco will be performing work north of the Metro garage in preparation for a new pedestrian link from the future MCC building to the Metro Garage. During this time, a portion of the sidewalk on the north of the garage will be blocked by equipment and pedestrians will be rerouted from these areas. Vehicular access to the garage will remain open during the work times.
UPDATE TO EUCLID SIDEWALK CLOSURE: Due to unexpected delays, the water service work for the MCC building was not completed on Tuesday, February 2nd. Clayco is completing work in the evenings this week and plans to place the concrete over the weekend of February 5th. During these activities a portion of the sidewalk will remain open at all times.